How to estimate a standby generator package

Start with the generator schedule, the one-line diagram, the specifications and the supplier’s written quote. Mark what the equipment package includes, what your crew must install and what still needs a price. Record the drawing revision and quote date so you can check them when an addendum arrives.

Compare the supplier quote with the field work

Suppose the supplier quotes an enclosed generator set, a factory-mounted tank and a startup visit. The freight line says “delivery to site.” Before carrying the package into the bid, resolve these items:

  • Delivery and setting. Confirm who unloads the truck, supplies rigging and sets the unit on the pad. Get the shipping weight and dimensions the equipment mover needs to quote the work.
  • Accessories and connections. Check the breaker, charger, heater, remote annunciator and exhaust accessories against the quote. Identify factory-mounted items separately from field wiring, supports, piping and work assigned to other trades.
  • Startup and testing. Ask what the startup visit covers. Check who supplies the load bank, temporary cables, field-test fuel and the final tank fill. Assign each cost once.

For a real example, page 47 of TxDOT Special Specification 7096 (PDF) assigns factory-test fuel to the generator manufacturer and field-test fuel to the contractor. On your bid, use the project documents to establish which party carries each item.

Price the specified automatic transfer switch

Match the quoted automatic transfer switch (ATS) to the rating, voltage, enclosure and configuration shown in the bid documents. If bypass isolation is specified, request the price, dimensions and shipping weight for that configuration. Check the delivery route and the work to set, support and connect the switch. If the bid form requests bypass isolation as an alternate, keep its change in price and scope separate from the base bid.

Check UPS, PDU and raised-floor scope where shown

  • Uninterruptible power supply (UPS). Check the cabinets, batteries, bypass equipment and monitoring connections on the schedule. Identify who furnishes, sets and connects each item.
  • Power distribution unit (PDU). Verify the shipping weight, supports, transformer if specified, and the number of field terminations. Check whether the quote includes the stand for a raised-floor installation.
  • Raised-floor work. Use the drawings and specifications to take off bonding conductors, clamps, supports, and any connections to monitoring or fire protection systems within your scope.

Use the electrical vendor quote checklist to record inclusions and open questions. Then carry the reviewed quote, field labor and job expenses into the bid. See how that review fits into Red Rhino Electrical Estimating Software.